Letter Strathy 14th May from Parkswatch contributor Graham Garfoot. HIE has refused to release the engineering reports on which the proposals to repair the funicular are based.
Highland and Island Enterprise’s Planning Application to repair the funicular is to be considered Friday morning (see here) and Cairngorms National Park Planning Officers have recommended it be approved. Parkswatch has previously covered why this is wrong: in the context of Covid-19 (see here) and (here) ; commercially(see here); from scrutiny of the planning papers, including the justification from an engineering perspective (see here); and in terms of the environmental impacts over a large part of Cairn Gorm (see here). This post just take a critical look looks at the Cairngorms National Park Authority Officers justification for their recommendation.
The meeting is being broadcast live from 10am (see here) – a first – and I have asked the Park if they will make this available afterwards as a webcast. That would be a major step forward in terms of transparency. Remarkably, there was only one letter in support of the application, from the Community Council, and they clearly stated the application should not have been put forward before the consultation on the proposed masterplan was complete.
The alleged justification for this Planning Application
The Officers’ main argument in support of the application is that since the funicular is already built, the principle of development has been accepted, and that this application is just about repairs to the piers. That I believe is wrong. As previous posts have shown the repair of the funicular has implications for the future of both Cairn Gorm the mountain and Cairngorm Mountain the business. This is reflected in the CNPA’s own summary of the objections:
Instead of considering these, the CNPA dismisses them as not relevant on the basis of a few sweeping arguments.
The need for a masterplan and the Cairn Gorm Working principles
Claim: “It is the Officer’s view that the application does not prejudice any future development or management of the ski centre that the masterplan may set out, as the continued operation of an existing facility at the ski centre is clearly consistent and compatible with the existing use and operational efficiency of the existing business at Cairngorm Mountain”.
This is almost certainly wrong as, given the cost of the repairs is £10m plus, it’s a case of either repair the funicular OR put in new lifts. Its very unlikely there will be money for both – or has the CNPA been told there is an unlimited budget for Cairn Gorm? The CNPA was also very clear in the working principles they adopted over a year ago (see here) that a masterplan should be required BEFORE any further Planning Applications were submitted by HIE. Instead of treating the Principles Document as a material consideration in planning terms, CNPA officers have dismissed its significance and effectively undermined their own Board.
Economic justification
Claim: “The costs of the strengthening works and peoples’ opinions on the value for money or use of public money are matters for the applicant and are not relevant to the determination of the planning application”
Comment: the Cairngorms National Park Authority has a statutory duty to promote sustainable economic development, so why have officers abdicated that responsibility in this case?
Development Area
HIE applied for planning permission for work around 65 of the piers supporting the funicular but none of the other ground that would be affected by the works, such as temporary tracks and track upgrades (see here again). A number of people objected to this but CNPA officers have tried to dismiss those objections in the Committee Report on the following grounds:
If 0.5% of the population can understand that I’d be surprised. The obfuscation appears quite deliberate and is how the Planning system promotes the interests of developers, in this case HIE, over those of the public. Dress Planning decisions up in technicalities and jargon and the public and Committee Members are put on the back foot. Its taken me a fair bit of time to unravel but I will do my best to explain the technicalities in ordinary language.
What paragraph 49 appears to be saying is that, because HIE “confirm” that all the works outside the 65 red lines round the piers which demarcate the areas included in the planning application are permitted developments associated with the proposed work (Class 14), therefore those works do not require planning permission. Note that CNPA officers don’t say in the report, “confirmed to our satisfaction”, rather they have accepted HIE’s word for it.
CNPA officers’ acceptance of HIE’s claims that temporary tracks come under Class 14 looks highly dubious. This is because the wording of Class 14 the General Permitted Development Order (see here) appears to apply to machinery and buildings temporarily placed ON land, not “temporary” alterations to the land itself:
Temporary alterations to land, such as new drainage channels or river diversions for hydro schemes, which are a necessary part of developments are normally included in planning applications. Indeed, until now the CNPA has included temporary tracks in planning applications, for example for hydro schemes. This is illustrated by the Glen Muick hydro scheme (see here) where Prince Charles was obliged by the Planning Committee to “include details for the compound areas and pipeline route and any temporary access track….………” in the Construction Method Statement. So why, is HIE being allowed to do something that the CNPA has never allowed even royalty to do before?
I doubt it’s lawful and if the Planning Committee agree to this it will set a very unwelcome precedent. If it’s approved its difficult to see how the CNPA would ever again be able to control how temporary tracks associated with developments are constructed or restored. That really isn’t good enough for a National Park.
The last two sentences in para 49 of the report are again jargon. Essentially they say that unless a member of the public asks the CNPA to determine whether works such as those proposed at Cairn Gorm need planning permission or not, they won’t do anything. (Section 37 says that if a Planning Authority receives a planning application they can agree to it or refuse it (see here). Sections 150-153 (see here) say that if anyone wants to find out whether an existing or proposed use of land is lawful, i.e whether it needs Planning Permission or not, they can ask the Planning Authority to decide this).
All this appeared to me to be a serious abdication of responsibility so I emailed the CNPA earlier this week and, to their credit, got a response. This which included the following:
“The applicant has provided sufficient details of those temporary works in addition to the permanent works for the CNPA to undertake EIA [Environmental Impact Assessment] screening of both the permanent and temporary works described and has determined that no EIA was required for the individual or combined works.”
Unfortunately, there is NO mention of any EIA screening having taken place in the Committee Report nor can I find any mention of this on the Planning Portal (normally Planning Authoritiies publish their EIA screening opinions). The Ecology report and Scottish Natural Heritage in their responses to the application both say there is no “appropriate assessment” is needed for “European” protected areas but don’t say whether an EIA might be needed or not. The Committee Report does, however, state (under conditions 4 and 6) that the development is in an environmentally sensitive area. That begs the question of why the CNPA believes no EIA is required. The Planning Application does not give many details of the temporary tracks or proposed track upgrades – so its almost impossible to ascertain how large an area will be affected – but it appears considerable. All the more need for an EIA, added to which is the sensitivity of much of the ground at Cairn Gorm.
The remainder of the CNPA’s response provides some helpful clarifications about the tracks, notwithstanding the fact I don’t accept they come under Class 14. It says the developer must have the “ground reinstated to its condition before the development was carried out” , for the track to remain a permitted development under Class 14. It also says: “If those works are significant enough to require planning permission (and not all upgrading works do), then they would only be permitted under class 14 if they are temporary”. The Committee Report says nothing about the track upgrades will be permanent or not. However, the Planning Application states:
It seems therefore that these track upgrades aren’t temporary and therefore DON’T come under Class 14. They should therefore be treated like other new tracks and significant track upgrades in National Scenic Areas and be subject to planning permission
Anyone who has walked the Shieling track, which runs parallel to part of the southwest side of the funicular, will know that it is not suitable for heavy machinery and would require extensive upgrading works to be so used. Those works will be even more extensive in its upper section which is steep, liable to erosion and contains bends which are too narrow for the proposed machinery.
It is also predictable that, given the need for DAILY checks on the supports to the piers to adjust them to the prevailing temperatures (see Graham Garfoot’s letter), HIE will in future apply for the temporary track up by the piers to become permanent (just like all the temporary construction tracks to hydro schemes in the Loch Lomond and Trossachs National Park which were subsequently made permanent).
Given the past saga at the Shieling (see here for example) it should also be obvious that there is not a chance of HIE restoring any upgraded or temporary track back to even its current condition. That record makes officers apparent failure to examine critically HIE’s claims that everything outside the red lines round the 65 piers should be classified as permitted development all the more surprising.
Unless the Planning Committee is satisfied all the works outwith the areas around the 65 piers come under Class 14 because they really are temporary and really will be fully restored, these works should be included in the Planning Application. Since what is proposed, is not clear, it’s difficult to see how the Planning Committee could approve this application as currently framed even if they were minded to do so.
The CNPA and HIE use the same legal firm for advice – Harper MacLeod, whose Chairman was until very recently the Chair of HIE. If CNPA was acting the way an independent planning authority should, then they would have/should have sought independent legal advice on the matters raised by this application. I’m willing to bet they have not.
HIE, have a duty of care to release the reports on the Funicular as they are a public body spending public money on a asset that they own/run?
The money would be better spent removing the Funicular and putting in a Gondola system that would be far more suited and cost the public less in the future.
Why keep throwing good money after bad trying to fix a system that was never a success in the first instant, they were advised to put in a Gondola system in the first place but chose not to because Nevis Range had one!!!!!!!!!
In the applicants statement which was read out at the planning committee meeting, HIE made mention of the Funicular being a key driver of the local economy and an efficient means of uplift. It is neither of these as has been evidenced by the collapsing number of passengers and snowsports customers that were using it prior to failure and by the fact that it has numerous inefficiencies associated with its operation as publicised by parkswatch on more than one occasion.
It was notable that there was a real lack of rigor by the members of the planning committee in so much as they asked no questions in relation to the objections statements that were read out at the meeting.
A ‘rubber stamp’ job.
A well composed article, Nick. As I suspected, however, predictably but disappointingly, the CNPA planning committee was unwilling to go against their planning officers’ recommendations. This case clearly smacks of a stitch up between HIE and CNPA. There has been a lot of twisting and turning by the CNPA planning officers to find a dubiously legal way of justifying stating that this is not a Major Development and that an EIA screening or pre-application consultation was not necessary. CNPA planning officers, and by implication the Planning Committee has taken too much of the information provided by HIE at face value. Clearly the scrutiny has been totally inadequate.
An example of this is the issue of whether Harper MacLeod had a conflict of interest being legal advisers to HIE and CNPA. It appears that only when this issue was raised this week did CNPA try to cover its tracks. It was stated at the planning committee hearing this morning that CNPA had used Harper MacLeod for legal advice on this application, but that HIE had said that they had not used Harper MacLeod for this planning application. CNPA was not aware who HIE had used and has taken HIE’s statement at face value, with apparently no checking. Any planning authority wishing to be fully independent of the applicant would have ensured at the start that there was no chance of conflict of interest in their legal advice, rather than wait until the issue was raised.
The other concern is why did HIE not from the outset just decide that they needed to make this application fit the requirements of a Major Development – they have had plenty of time to comply with the requirements (e.g. EIA screening advice and pre-application consultation). Let’s not kid ourselves that this was about saving money on the application fee – given the money HIE has squandered and continues to squander on Cairn Gorm. For me. the answer lies in the inability of HIE to project manage with any real competence and/or HIE wanting to keep as low a profile on this embarrassing issue as possible. Running two public consultations (pre-consultation on funicular repairs and masterplan consultation) close to each other would have exposed the foolishness of what HIE was planning to do.
We now have to rely on the business plan (when its submitted) being properly scrutinised by the Scottish Government and Parliament, and the outcome of the Audit Scotland report on HIE’s conduct in managing the Cairn Gorm business over the past 6 or 7 years.
What they will do is fix it then say only two people can use it at any time social distancing.xxxxxxxxxxxx
The Coire na Ciste chairlift should never have been removed but should have been enhanced. The funicular was a vanity project and whilst providing uplift, as the only means of uplift was undependable as in prime ski conditions the tunnel became blocked with ‘too much’ snow. That combined with a commercial imperative to prioritize summer uplift whilst being ‘casual’ about health & safety checks, and negligent fiscal management has led us to this situation. Rather than good money after bad, it would be better to go with the gondola option or wider chair systems as now used in the Alps. The management of cairngorm mountain was deplorable. Running a ski resort and rocking up to the ski road barrier at 9AM to decide whether or not a snow plough was needed to clear the road of snow on a godsend of a day, and then decide theres no skiing today and all the eager skiers should turn around and go home (a situation which happened all too often) was not only lazy but commercial suicide, for both the mountain and the local economy. To continue to prevaricate over band-aids shows that nothing has changed.
that guy xxxxxxxxxxa bit xxxxxxxxxxxxxxxx
jus get it fixed n move on naesayers!
its a mellow mtn and needs beginner uplift.
the choo choo is ideal
end of
move on to trolling something/someone else
Jah Snowman, I have only published this comment to say that I am not going to publish comments in this vein in future. I have wanted to allow people to express a broad range of opinion and also to show how they feel but unfortunately this has in some cases descended into insults and comments that in my view are not intended to further informed debate. I have probably not taken action soon enough. I would also appreciate it if people use their real names when commenting as I think that aids transparency and reduces the type of abuse that is so common on much of social media.
Can anyone point to another instance in GB where a quango using public money has bought into a potentially viable business with high 6 figure turn over, and then wrecked it? The Public money entrusted to the HIE Quango by Holyrood is supposed to support enterprise across the Whole of the highland region. It was never aimed to service just the bit conveniently close to the HIE office. In what way are Civil servants as managers of a regional development agency qualified to run any business with 7 figure turnover potential? When busy aspiring to be ‘big business managers’, who is then left to carry out the function these people were primarily employed to do? What can be said by this agency to all the other small businesses across the Highlands that apply and could deserve “prime pumping” to become self sustaining again after Covid. ( see chain of 7 hotels declared bankrupt today) Are they to be told ‘The money is already committed;allocated for years to come , or aactually gone ‘??? The huge sums wasted on Cairngorm over the past decade should be subject to a full criminal conspiracy audit, Any individuals – who appear to have derived benefit from the largess of this Public purse without excuse or remorse, should be sacked.