The Funicular Railway Report July 2018 – HIE’s cover up and the implications

October 28, 2019 Graham Garfoot 4 comments
Photo Credit Save the Ciste 2018

Background

On the 27 January 2019 I applied to Highlands and Islands Enterprise for the two “ADAC Structures” Inspection reports which resulted in the Funicular Railway being closed. The redacted reports were finally released on Friday 11th October after a request to the Scottish Information Commissioner. This post will look at the Funicular Railway Inspection Report 2018.  This has not yet been published on the HIE Cairngorm FOI page (see here), which HIE claim is being updated and has “lost” lots of information previously published, but you can read it (here).  (NB 10 MB document). The second ADAC Inspection Report on the Ancon Bearings will be covered in another post.

My initial reaction on reading the reports was that HIE had released very little, as whole pages have been redacted and photos are missing. Then I recognised the photos that had been left in were from the 2015  (see here – 6 MB) and 2016 (see here – 9 MB) ADAC Structures Funicular reports which had already been sent to me under Freedom of Information.  I therefore printed off the other pages to compare with previous reports.

It appears that HIE hasn’t even properly checked the information that has previously been released as there are several inconsistencies. From the shape and size of some of the redactions, however, it is possible to make an educated guess at the information that is missing.  Together they do shed more light on what has gone wrong with the funicular and why.

Analysis of what has been redacted

The first three pages are almost identical to the November 2015 report and then the redactions start at:

Item 2. Executive summary:

There is very little left to be read on this page, but, earlier reports consisted of three or four short paragraphs. The  increase in size to a full page strongly suggests that there have been some big changes in the past eighteen months!

Extract from Summary

Para.2.2.2 raises new questions.  Presumably, the damage caused by operational use of machinery is to the beams and parts of the track that are covered by heavy snow falls and therefore it will be the same ones that are being damaged all the time. Have all these impacts by machinery caused some of the problems with the operation of the Funicular?  If so, how much if any of this was due to carelessness on the part of the operator, Natural Retreats? (see also section on Appendix B).

Item 3. Scope and references:

This is very similar to reports from earlier years reports but with the addition of a sketch showing the structural elements.  This is really helpful in allowing ordinary people to understand the various parts being described and where they are to be found.

Item 4. Funicular railway observations:

A section with a similar title appeared at Item 5 of the Dec. 2016 and item 4 of the Nov. 2015 reports and from this the redaction in the very first paragraph of the 2018 report would appear to be:

The general condition was thought to be poor for a structure of this age with wide spread minor deficiencies giving a general impression of poor quality control during the construction phase”.

The same comment has been made by the author of the report since November 2015.   So why does HIE now want to redact this?

Para. 4.1 Thrust blocks:

The thrust block at pier 94, mentioned in previous reports, is no longer listed, although this appears just a typing omission. Paras. 4.1.3 and 4.1.4 would appear to be same as those redacted from the December 2016 report (paras. 5.1.3 and 5.1.4). So what’s going on and why hasn’t it been addressed?

Para 4.2 Main piers:

A comparison with Para 5.2.2 of the 2016 and, parsa 4.6.2 & 4.6.3 of the 2015 Reports shows the number of damaged piers has steadily increased.  In the November 2015 report 5 of the main piers were noted to have faults.  This increased to 9 in the December 2016 report and to 15 in July 2018.

Pier 72 stands out as there was no mention of it in 2015, then in 2016 it was “ showing signs of frost damage and seepage through horizontal crack” then in 2018 it also had a ”Vertical crack on downhill face of lowest unit. Vertical crack on left and right face, mid height”. This seems to imply that the whole pre-cast shell is breaking up! Was this the pier that had layers of concrete removed by contractors earlier this year?

Para 4.3 Main cross heads:

This section suggests there has been a failure to monitor cracks as recommended.

Para 4.3.2 is not quite right when it statesOther than pier 93, the following items were recorded in previous years”. That is incorrect. Pier 63 was not mentioned in the earlier reports and now records a “chip bottom middle!“

Para 4.3.3 on Pier 93, has been almost totally redacted except for the last sentence “Crack monitoring studs have been installed and will be monitored until a feel for the situation is achieved”.   The December 2016 report, however said this (Para 5.3.3):-

“Description:  Crack through pier cross head, running up one face and  through the PT bolt holes on the top and down the other side, this is apparent on the line of both PT bolts. This appears to be a development on the previous year, when the cracks were only recorded on the line of one bolt. Ref photos (5).

Location:Pier 93.

Recommendation: This would not be a concern in itself as the cracks are of a minor nature, but the appearance of a developing situation is of concern. It is recommended that crack monitoring is implemented immediately and that this is monitored at close intervals until a feel for the situation is achieved”

So, after the recommendation to monitor cracks at CLOSE INTERVALS why has HIE now chosen to redact information on what has been happening?

Para 4.5 Insitu concrete joints.,  Para 4.6 Problems with the precast beams, general., Para 4.7 Problems with grout plinths to the rails.

Due to the amount of redaction, it is mostly impossible to refer back to the earlier reports for comparison in these paragraphs.    I am raising this with the Scottish Information Commissioner to try and get the hidden information.  However, there are three appendices linked to these paras which illustrate how the problems have got worse:

Appendix A: Schedule of fractured flanges. (Refers to clause 4.5.4)

In Dec 2016 there were problems identified with 23 flange ends of the precast beams this increased to 33 by the time of this inspection, almost 50% in 18 months!

The next two appendices refer to the precast beams:-

Appendix B: Schedule of mechanical damage to arrises (Refers to clause 4.6.3 and was highlighted in Executive Summary)

“Mechanical damage to the main beams, presumably from snow clearing activities”.

In Dec. 2016 (para5.6.2) damage was identified in 7 beams, increasing to 31 by July  2018. As it is usually the same sections of the track that get snowbound, then that damage will obviously continue into the future!

Appendix C: Schedule of exposed reinforcement Ref clause 4.6.4

In Dec. 2016 (para 5.6.3) there were 7 instances of damage noted, again increasing to 20 by July 2018 although 4 of these had been repaired after the 2016 report.

 

Para 4.8 Miscellaneous

These paragraphs, with redactions,  are exactly the same as the previous years, including para 4.8.3:

“ There is a partial walkway….etc. It is my recommendation that this work be carried out”.

This walkway was part of the original construction of the Funicular which was signed off on completion of the project and yet has still not been completed!

 

Item 5. Recommendations general.

The recommendations from the 2016 Report  appear to have been copied over to form part of the 2018 report,  as the paragraph numbers are the same as is the content after all the redactions:

Recommendations 2016 ADAC Funicular Report
The 2018 Report – heavily redacted

 

The redactions provide an interesting insight into the secrecy culture at HIE – they have now even redacted 5.2 where there is NO recommended action. Other redactions appear to an attempt to cover up the lack of any progress on recommendations going back 2 years.

What is even more interesting is the very final sentence from the 2016 recommendations which has not been carried over even as a redaction:

para.6.3.3 If wide spread beam strengthening is required this is likely to be very costly”.

Time for HIE to tell the public if beam strengthening is required and just how costly that might be.

 

Conclusion

Despite all the redactions, the 2018 Report compared to previous reports,  provides further evidence that HIE has consistently failed to act on recommendations that it needed to repair the funicular.

Audit Scotland has said it will investigate how HIE managed their contract with “Natural Retreats.  Their failure to act on maintenance recommendations, including those with serious health and safety implications, needs to be a key part of that.

The report also confirms that there are major problems with the Funicular which are:-

(1) Not going to be cheap to repair, remembering this is not the fully detailed inspection, e.g. the photo below shows monitoring equipment installed on one of the piers,

Photo Credit Save the Ciste 2018

(2) have substantially increased in the 14 to 17 year period after it was completed, and,

(3) due to its position on the mountain are going to recur.

4 Comments on “The Funicular Railway Report July 2018 – HIE’s cover up and the implications

  1. An excellent commentary on a difficult to read report given all the redactions, Graham, and well done for comparing this heavily redacted report with the earlier reports. I believe we are facing a further closing of ranks within HIE and the Scottish Government. There are politicians and civil servants adept at ‘weathering the storm’ – even when the criticism comes from Audit Scotland. We just need to keep going.

  2. Yes, well done Graham. It is becoming ever more apparent that a gondola replacement is the sensible and most likely the cheapest option here. Why not leave the funicular as is, build the gondola up the Ciste to the Ptarmigan, remove the planning restriction on summer access to the outdoor area of the summit, get the place making money and if they must repair the funicular use the incoming profits and some funding assistance over a sensible period of time. Thus saving face for H.I.E. and others and appeasing the increasingly disgruntled locals and visitors. Why don’t H.I.E. just put their hands up admit they have got it wrong, take the initial heat, let the storm blow through and get on with resolving the issue in an honest and sensible manner. If they don’t the noise will only get louder and the fall out will be greater !

    1. The most sensible option is a 2 x 6 person chair / 8 person gondola hybrid. It would allow access to skiers without removing skis, or the Gondola for beginners and non-skiing visitors. When the ski season is over the chairs could be removed which would reduce running costs. The Funicular as you say could then be repaired as income from skiers starts to flow. It is highly unlikely this will happen as HIE has an irrational opposition to any kind of infrastructure in the Ciste. For them to build in the Ciste would be admitting that the views put forward by the Save The Ciste campaigners were correct all along, and that is why it will never happen. HIE’s arrogance means that skiers will continue to boycott Cairngorm, spending their money at resorts where they are catered for and businesses in Strathspey will continue to suffer in the winter months.
      I believe there is a small chance to change HIE’s position, but that would require ALL interested parties to come together acting in unison and with one voice. Holding a conference in Aviemore inviting TV, Press, MSP’s, MP’s, in fact anyone with the clout who will listen and force a change in attitude at HIE is the only way forward.
      Let’s call it——– SKIERS REBELLION.

      1. Sounds good to me Graham ! I’m sure McDonald hotels could do with the revenue from a conference, they might even offer up the venue free of charge. You are right the arrogance, belligerence and institutional denial of H.I.E. is staggering. They just continue to add to the catalogue of calamities of their own making. They would be far better realizing the limitations of their capabilities, admit the error of their ways, apologize and put someone in charge of this that can get the job done without alienating and irritating even more people. Someone needs to be screwing down the quotes from potential contractors and doing it with the attitude of a commercial project manager not a public servant who cannot grasp the concept of hard negotiation and the limitation of tax payers funds ! BRING BACK THE CISTE let’s get things moving.

Leave a Reply

Your email address will not be published. Required fields are marked *