Climate Change and Glen Falloch (4) – hydro failures and their impact

October 1, 2019 Nick Kempe 1 comment
Upper Glen Falloch hydro intake 25th September 2019 – photo credit Kevin McGrath

In my last post on Glen Falloch (see here) I considered the impact that the very heavy rainfall of 5th August had had on the hydro intake pools.   I argued that the serious infilling and damage in some cases appears to be a fundamental design flaw which results from schemes being constructed in unsuitable places.  As a consequence some are unlikely to be viable long-term unless turned into semi-permanent work sites and risk being abandoned completely becoming liabilities rather than assets in our attempts to combat global warming.   This post looks at the impacts the flooding has had BELOW the intakes which has equally serious implications for the future of run of hydro schemes.

View up to intake May 2019. The bare foreground is a consequence of further work the Park approved in 2018 (see below).   Photo Author.

Compare the two photos above taken just four months apart.  A large proportion of the rip-rap bouldering which had been placed against the dam wall to the left of the intake has been removed by the flood, along with much of the bouldering along the bank of the river below.

The artificial embankment at the Upper Falloch intake used to reach the top of the concrete walls and has been stripped away from between them to the new bank opposite.  Photo credit Kevin McGrath
Looking downstream from the intake the rip rap bouldering on the right bank, which used to mirror that on the left bank, has mostly been swept away making this side of the river appear far more natural.  Photo Credit Kevin McGrath.

The force of the flood water to remove the rip rap boulderling must have been quite something.  The boulders  were placed here to protect the river bank after the construction of the intakes but have failed. And its not just on the Upper Falloch where this has happened, but on four of the other eight Glen Falloch intakes.

Large chunk of restored bank removed from below Allt Andoran Intake, leaving bare bank behind – Ben Chalum in distance.   Both banks below this intake have been seriously damaged.  Photo Author.
View down from Ben Glas intake on walkers path to Beinn Chabhair Sept 2019.  It looked to me like boulders had been stripped from the left bank mid-photo.
A comparison with a photo taken in 2016 confirms the extent of bouldering which has been washed from the banks
Looking up to Allt a Chuillin main intake along section of pipeline that was, until recently, under the “restored” bank of the river (photo of this from above featured in my last post). The pile of boulders on the right appears to have been excavated from the pool and is perhaps intended for use to cover up this pipeline again.  Unlikely to work!
Damaged bank below the second of the Allt a Chuillin intakes

That’s five out of the nine Glen Falloch intakes where the restored banks below the intakes have been seriously damaged.  In those that haven’t, a large part of the explanation appears to lie in where they have been located – between rock walls!

The other Ben Glas intake (see above), with a large pool and constructed into rock, is little damaged compared to its neighbour.  Had the highest section of concrete retaining wall be faced with stone, as per Park Best Practice Guidance, the landscape impact of this impact would have been reduced further.

Three out of the four intakes with relatively undamaged banks appear to have survived the floods precisely because they did not make such extensive use of rip rap bouldering.  What looks better appears to work better!  In the final case, the third Allt a Chuillinn intake, the one that has not been working for over a year, its been so overrun by boulders from above that its hard to tell what’s happened.

While much less rip rap bouldering has generally been used ABOVE the hydro intakes, there is also evidence that where used it has been seriously damaged by the flood event:

 

Looking across the intake pool to the rip rap bouldering embankment September 2019 – it now looks far more natural than it did four months ago. Photo credit Kevin McGrath.
View over to same embankment May 2019

Besides the large amount of silt washed over the bank in the top photo – which could help it eventually revegetate and stabilise – many of the boulders visible in the earlier photo are no longer there and appear to have been washed away (I blew both photos up to compare them).

 

So what’s the problem?

Looking at the before and after, contrasting the artificial restoration work approved by the Loch Lomond and Trossachs National Park Authority with little regard to the landscape impact and what’s there now, part of me rejoices.  Its nature at work, re-wilding if you like and testimony to human folly.   It won’t be left, however, since there is money at stake.

The first  problem is that nature at work will, sooner now maybe rather than later, change the course of many of these rivers leaving the hydro intakes high and dry.  It, like the infilling, will turn them into  liabilities not assets that could end up contributing to net global warming.

New river formation on the Upper Falloch (intake pool just visible to right)?  The erosive impact of the river overflowing here has been accentuated because this a diversionary channel was constructed on this line while the intake was being built.  This section of ground is not “natural” and helps explain that where peat has just been placed on the surface its been washed away.  Destruction of peat of course releases yet more carbon into the atmosphere.

That then creates a second problem, how to restore these schemes if the original restoration techniques clearly haven’t worked?  Does anyone know the answer? (I consider this more below).

The third problem is that large amounts of material, not just rocks but also sediment, have been washed down into the rivers below.  During construction, the Scottish Environment Protection Agency required the contractors to take various measures to prevent silt entering watercourses.  The combined effect of all those measures now appear to have been completely undermined by all the material that has now been washed down into the rivers through the banks that failed.

The fourth problem is that along with natural material – rocks, gravel, silt etc – a significant amount of plastic sheeting appears to have been washed into the river system.

Eroded bank and ripped up sheeting below the Upper Falloch intake.  Photo Credit Kevin McGrath

You may have read about Scotland’s infertile pod of killer whales which scientists now believe have never reproduced due to the volume of plastic they have ingested from the sea.  Well, we are doing the same to our lochs.  In this case the Falloch flows down into Loch Lomond which is famed and specially protected for its fish, from powan to salmon.  What impact will all this hydro plastic have on these species in the medium term?  That’s another thing the Planning System, in its headlong rush to promote hydro, failed to consider.  It needs to do so now before any approval is given to how these schemes might be restored and the Glen Falloch Estate should be starting with a comprehensive clean-up.  Unfortunately I don’t expect the hyprocritical senior managers in the LLTNPA will come down nearly as hard as they have done on campers who cause far less damage to the natural environment.

I am not blaming the individual planners here, rather the system in Scotland as a whole which failed to consider what might happen to run of river hydro schemes if they were hit by the sort of flash storms which will become increasingly common with climate change.  I cannot recall seeing a single Planning Application which considered these issues properly.  After what’s happened in Glen Falloch, they can no longer be avoided.

What’s caused these problems?

In the same month the floods hit Glen Falloch, the Scottish Environment Protection Agency issued updated Good Practice Guidance on engineering for intakes and outfalls (see here).  It contains just ONE single reference to the use of rip rap bouldering:

It was re-assuring to find SEPA confirming my observation that hydro intakes located between rock walls are far less liable to suffer damaging erosion.  What they didn’t explain, however, is when, if ever, rip rap bouldering might be appropriate and if so how it should be designed.

The flood that has done so much damage to the engineered areas around the upper Falloch intake, has done relatively little damage to the river banks lower down:

Looking down the Upper River Falloch where relatively little damage is evident to the river banks. The hydro pipeline has been dug UNDER the burn in the foreground and the banks by the rush are the work of humans not of nature.  Photo  credit Kevin McGrath.

Kevin McGrath and I have visited all the Glen Falloch intakes over the last two weeks and this observation appears true for all the rivers.  There is some damage of course, some of it quite striking, but its nothing like the extent of the damage that has been done to the engineered banks.  Perhaps 5% of the natural river banks have failed compared to 50% of the banks restored by humans!  We need to understand why  but clearly we interfere with nature at our peril.

Whatever happened to the precautionary principle in the headlong rush for hydro?

Vegetation has been swept clean off this island in the middle of the Allt a Chuillinn well above the main intake

As the SEPA guidance explains the force of the water below hydro intakes is increased, a consequence of the way intakes affect the flow.

While I have no expertise in water dynamics, its not difficult to imagine why these floods might have affected the rip rap bouldering  more than the natural banks.  While natural banks deflect water flow,  flood water enters and is forced between the rip rap boulders and starts prising them away from each other.  It only needs one boulder to be dislodged and then the rest start to collapse.

The problem appears, however, to have been made considerably worse by use of plastic sheeting:

Plastic sheeting on bank below Ben Glas intake bridge. The level of the flood here reached the bottom of the bridge – as you could tell from vegetation left high and dry after the flood.

At first glance I thought, how ugly!  Then I realised the top of the bank has been swept away.  The problem is as soon as water gets between whatever is on the surface and the sheeting, its much easier for whatever is on the surface, whether boulders or turf, to get swept away.

Another example at Ben Glas.  The sheeting also stops roots penetrating into the soil below binding it.
A closer view down from Upper Glen Falloch showing how boulders have been swept off the plastic sheeting
Left bank below Allt Andoran, with cloth sheeting and section of pipe visible centre

This is not, however, just a problem about plastic sheeting.  Water forced through the boulders by the flood then collides and bounces off the intake pipes which form an erosion surface.  I don’t think its coincidence that two different sections of intake pipe  have been revealed by the flood event in Glen Falloch.   It appears from the photo above that even permeable membranes may facilitate erosion of material placed on them.

Perhaps its time to put a moratorium on any plastic sheeting being used to line the ground as part of the restoration of hydro schemes?    Whether that will address the whole problem, however, is another question.  What wouldn’t be acceptable is a solution that involves embedding the boulders in concrete.

 

What needs to be done?

I don’t blame front line Planning staff or staff from SEPA for failing to anticipate these problems.  They are under constant pressure to approve developments and, even if they have time to think about the consequences, have little power to do anything about them.  The failures lie higher up and with the landowners and developers who have promoted run of river hydro schemes as environmentally friendly projects without any proper consideration of the consequences.  After the destruction caused by the storm of 5th August in Glen Falloch, practice needs to change radically.

I would like to see the LLTNPA join me in calling on the Scottish Government and SEPA to investigate what has gone wrong, the implications and the potential solutions.  Meantime, however, I would like to see SEPA issuing interim advice on the design of hydro schemes still in the pipeline (their August Guidance is unfortunately no longer any use in this respect) and what Planning Authorities and Developers need to do when schemes fail.

In my next post on Glen Falloch I will consider the impact of the rainfall on the new tracks up to the hydro schemes.

1 Comment on “Climate Change and Glen Falloch (4) – hydro failures and their impact

  1. Rember a guy called Canute? That was back in the 10th century and we have not learnt anything. There is no stopping the power of nature, a fact that is being proved over and over. There are only two ways that could be tried to stop the damage as shown above. Either would be unacceptable but (1) is to concrete the boulders into place and for some distance upstream to stop erosion behind them, and (2) steel piles driven into the ground to form an inpenetrable barrier. As I have said both are unacceptable. The answer, either proper dams, build them in solid rock gorges or don’t build them at all. I look forward to your post on the tracks!

Leave a Reply

Your email address will not be published. Required fields are marked *