The public are paying for the current work at Cairngorm

December 28, 2016 Nick Kempe 1 comment
The article that appeared in the Strathy last week

After the Strathy’s excellent coverage of the Save the Ciste Group’s criticisms of what is happening at Cairngorm  (see here) it was inevitable that Natural Retreats would try and suggest that they are in fact doing lots to improve the skiing experience at Cairngorm and the article above duly appeared last week.   While the work has been contracted for by Natural Retreats, who are therefore responsible for the quality of the  work undertaken, almost all the work listed has in fact been paid for by Highlands and Islands Enterprise (see here).   Indeed out of the £700k Natural Retreats claims to have spent on maintenance and improvement work  this year, it appears £601,286 has been paid for by HIE.  If this is right, it appears Natural Retreats has invested just £100k, which could easily be paid for out of £400k savings the accounts show they made the first year they owned Cairngorm Mountain Ltd.

 

The truth behind the spend on ski infrastructure listed in the article is as follows:

  • Replacement of West Wall poma return station – paid for by HIE grant – planning permission breached by Natural Retreats’ contractors
  • Strengthening Cas T-Bar Gantry – £73,377 paid for by HIE for all works associated with gantry – Natural Retreats had still not in mid-December properly restored the site (see here)
  • Installation new safety circuit cable –  £315,641 paid for by HIE (electrical upgrades to surface uplift)
  • Replacement of motors and drives at Ridge poma, Car Park Tow and Polar express – unclear if this part of the electrical upgrades to surface uplift and therefore who paid
  • Installation of 4km new fencing – this is being paid for by Cairngorm Mountain Ltd, cost unknown.  The work however is not yet complete as implied in the article eg for photographic evidence showing West Wall poma uptrack fencing was not complete earlier this month (see here)
  • Removal of obsolete rope from Coire na Ciste chairlift – this is new, unclear who is paying
  • Installation of new haul rope for Polar Express – unclear who is paying for this
  • Completion re-instatement around Shieling rope tow and Cas Gantry – while the original works were paid for by HIE (£78,353 for Shieling ground works and £73,377 for Cas Gantry) I have submitted FOI request to HIE asking them to clarify if their payment included the costs of work undertaken by Natural Retreats without planning permission.

 

While I will submit a further FOI to HIE to try and clarify further what Natural Retreats has invested at Cairngorm, on the facts as presented by Janette Jansson it appears unlikely they are paying for all the items which were not clearly covered by the FOI request.  Indeed there are other items, not referred to by Janette Jansson,  such as replacement lift huts ,which we know HIE have paid for.   I think it is safe to conclude therefore that almost all of the investment that is going on at Cairngorm is coming from the public purse.

 

What Janette Jansson has failed to answer is the questions I raised previously:

“Can HIE and Natural Retreats answer publicly, whether they can evidence:

a) each are investing sufficient monies at Cairngorm, in their own areas of responsibility, to prevent further deterioration of the ski infrastructure, and

b) whether the cuts in staffing which were evident in Cairngorm Mountain Ltd’s accounts the first year Natural Retreats took over, has had an impact on the progress that has been made in replacing fencing at Cairngorm and other aspects of maintenance of the ski infrastructure for which they are responsible.”

 

If Natural Retreats are contributing so little to Cairngorm – indeed they appear from the accounts to have been taking money out of it – the public interest question is why should the public and the politicians who represent us allow the HIE lease with Natural Retreats to continue?

1 Comment on “The public are paying for the current work at Cairngorm

  1. It’s worth noting that the £601,286 is the investment made by HIE on all Civil, Mechanical, Electrical and IT works carried out on the Mountain since March 2014 and up to 17 August 2016. This capital sum does NOT include the sums of £73,377 paid in respect of: ALL WORKS associated with the Cas Gantry, including groundworks, Surveying, Tendering and Mechanical Installation. In addition, and also NOT included in the £601,286 was the sum of £75,612 which was paid in respect of ALL WORKS associated with the proposed extension and fixed return bullwheel installation, including all submitted contractors and suppliers costs for total realisation of the project. It’s therefore clear that HIE have made a Capital Investment of £601,286 + £73,377 + £75,612 = £750,275 in the period between March 2104 and 17 August 2016.
    Given that HIE agreed to invest £1.1m on upgrades to uplift [£1.7m, if we include buildings upgrades] at the time that they entered into the lease agreement with NA then the capital expenditures to date do fall within that sum.
    Readers may wish to question why £75,612 of public money can be invested into a 20m extension and a new bullwheel assembly on the WW Poma while at the same time NA themselves fail to make the necessary investment to replace the Poma uptrack fencing and to replace the critical boardwalk. Without the investments in fencing and in a new boardwalk that would have to be made by NA then we might question the value of the £75,612 of Public Expenditure on this tow. Doesn’t stand any scrutiny whatsoever and for it to be suggested that capital expenditures of over £700,000 have been made this year by Natural Retreats and by HIE is highly disingenuous at best as the capital introduced has come from the public purse not from NA.